The latest Microsoft Certification 70-178 exam training methods

The trouble can test a person's character. A bad situation can show special integrity. When to face of a difficult time, only the bravest people could take it easy. Are you a brave person? If you did not do the best preparation for your IT certification exam, can you take it easy? Yes, of course. Because you have IT-Tests.com's Microsoft 70-178 exam training materials. As long as you have it, any examination do not will knock you down.


To help you prepare for 70-178 examination certification, we provide you with a sound knowledge and experience. The questions designed by IT-Tests.com can help you easily pass the exam. The IT-Tests.com Microsoft 70-178 practice including 70-178 exam questions and answers, 70-178 test, 70-178 books, 70-178 study guide.


Exam Code: 70-178

Exam Name: Microsoft (Microsoft Project 2010, Managing Projects)

IT-Tests.com can not only achieve your dreams, but also provide you one year of free updates and after-sales service. The answers of IT-Tests's exercises is 100% correct and they can help you pass Microsoft certification 70-178 exam successfully. You can free download part of practice questions and answers of Microsoft certification 70-178 exam online as a try.


When you click into IT-Tests.com's site, you will see so many people daily enter the website. You can not help but be surprised. In fact, this is normal. IT-Tests.com is provide different training materials for alot of candidates. They are using our training materials tto pass the exam. This shows that our Microsoft 70-178 exam training materials can really play a role. If you want to buy, then do not miss IT-Tests.com website, you will be very satisfied.


70-178 (Microsoft Project 2010, Managing Projects) Free Demo Download: http://www.it-tests.com/70-178.html


NO.1 You manage a project that specifies all constraint types to As Soon As Possible. You discover that one
of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted
finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: A

Microsoft dumps   70-178 answers real questions   70-178   70-178 answers real questions

NO.2 The first major phase of your project is scheduled for a duration of 45 days. However, you do not have
task information for other phases. You need to indicate that the duration of the entire project is 200 days.
What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: C

Microsoft practice test   70-178 test   70-178 exam   70-178 test

NO.3 You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task.
Answer: C

Microsoft demo   70-178 exam dumps   70-178 exam simulations

NO.4 A section of your project contains only a summary task along with four subtasks and a milestone. You
discover that the section is located in the incorrect phase and has the incorrect Work Breakdown
Structure (WBS) numbering. You need to move the section to another phase of the project. You also need
to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: C

Microsoft original questions   70-178   70-178 answers real questions   70-178   70-178 original questions   70-178

NO.5 You manage several projects. Each project has shared resources and work distribution. You need to
ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on
each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view
to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level
Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C

Microsoft certification   70-178 test questions   70-178 study guide   70-178 test questions

NO.6 You have a Project 2010 schedule that contains the following tasks:
Inactive tasks
Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are
created. What should you do.?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C

Microsoft certification training   70-178 pdf   70-178   70-178

NO.7 You need to set the default constraint type for all new tasks to As Late As Possible. What should you
do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish
Date.
Answer: D

Microsoft   70-178   70-178   70-178 exam prep

NO.8 You manage a project according to the schedule as shown in the exhibit.
You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Answer: D

Microsoft test   70-178 exam simulations   70-178   70-178

NO.9 You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You
highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task
Answer: C

Microsoft answers real questions   70-178   70-178   70-178

NO.10 The project you manage has only part-time resources. The part-time resources work four hours a day
from Wednesday through Saturday. You need to create a new calendar and set the calendar as the
default for your project. Which two actions should you perform? Each correct answer presents part of the
solution.
A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: CD

Microsoft   70-178   70-178 certification training   70-178

With the arrival of the flood of the information age of the 21st century, people are constantly improve their knowledge to adapt to the times. But this is still not enough. In the IT industry, Microsoft's 70-178 exam certification is the essential certification of the IT industry. Because this exam is difficult, through it, you may be subject to international recognition and acceptance, and you will have a bright future and holding high pay attention. IT-Tests.com has the world's most reliable IT certification training materials, and with it you can achieve your wonderful plans. We guarantee you 100% certified. Candidates who participate in the Microsoft 70-178 certification exam, what are you still hesitant?Just do it quickly!